Project Overview: South Coast Water District (SCWD) is replacing a leaking water main inside a bridge that crosses the I-5 on Via California in Dana Point
Construction Hours: Construction will be limited to Monday through Friday from 7:30 AM to 5:00 PM.
During construction, traffic will be restricted to one lane. Proper traffic control including flagmen will be in place throughout construction.
Project Cost: The cost of the project is estimated to be $450,000.
Project Timeline: Construction will begin on August 17 and will be completed in September 2020.
Project Contacts:
Project Manager: Taryn Kjolsing, tkjolsing@scwd.org ,949-541-1327
Project Inspectors: Danny Takahashi, dtakahashi@scwd.org 949-289-0091 or Mario Rodriguez mrodriguez@scwd.org 949-322-0485