Tunnel Construction Update 5-6-17

Sound Wall and Mitigation

When will the sound walls be completed?
The sounds wall are up. Contractors expect the gate installation to be complete by middle of next week (@ May 24). During the week of June 5, the contractor will be filling in gaps under the fencing.

Crane

When will the electric crane start to be used?
The electrical transformer is expected to be installed the week of June 5.

Excavation

Will the shaft site be covered during the night? 
The shaft will be enclosed at all times by a 6-ft high fence.

Memorial Day Holiday

Is there a hiatus due to Memorial Day weekend?
Yes, there will be no work on the site from May 29 to June 2. Security will be on site 24/7 during that time.